Increase of the assembly discharge burnup by about 1.5%
Fuel cost savings of 500.000 Euro per cycle
Implemented in Ringhals 2-4
The software team at NRG works to improve our ROSA code every year. Our team:
Vattenfall, based in Sweden, contacted the fuel management team at NRG. Vattenfall has 4 operational reactors at Ringhals. Because of the complex core design of these installations, reducing operating costs was challenging. We applied our ROSA software to the problem. Together with help from the Vattenfall engineers, the software tool was adapted to the Ringhals 4 installation. ROSA outperformed Vattenfall’s reference case with a higher than required increase of the assembly discharge burnup of 0.6 MWd/kgU per reactor core assembly. This relates to fuel cost savings of about 500,000 Euro per cycle.
ROSA outperformed Vattenfall’s core reload solutions, and provided us with substantial fuel cost savings.
The software team at NRG works to improve our ROSA code every year. Our team:
The software team at NRG works to improve our ROSA code every year. Our team:
As a result of these excellent results Vattenfall decided to purchase ROSA for both Ringhals unit 2 and unit 3. ROSA is now successfully implemented and used by Vattenfall to their satisfaction.